Pipeline Work Underway Along Lowell Boulevard

Extraction has approval from the City to begin pipeline work along Lowell Blvd near the Livingston Pad and that work is underway. The City also permitted two construction trailers that have been installed just south of E-470 near I-25. More activity is expected along the pipeline route in the near future.  Please see the pipeline map below or access it here.

From the May 4 Update Posted on the City’s Oil and Gas Webpage (p. 2-3)

Tentative Schedule Forecast: upcoming Public Private Improvement Permits (PPIP) applications and work:
PPIP Submittal PPIP Approval ~ Construction Start
Crossing C1 & C2 5/2 End of May ~ Mid-June
Segment 1, 2 & 3, F2 5/2 End of May ~ Mid-June
Crossing F1 & C3A ~ 2nd week of May ~ 1st week of June ~ June/July
Segment 4 & 5 ~ 2nd week of May ~ 1st week of June ~ June/July
Segment 6 & 7 ~ 3rd week of May ~ 2nd week of June ~ July/Aug
Crossing C3 & C4 ~ 3rd week of May ~ 2nd week of June ~ July/Aug
Segment 8 & 9 ~ 4th week of May ~ 3rd week of June ~ July/Aug
Crossing C5 & C6 ~ 4th week of May ~ 3rd week of June ~ Aug/Sep
Crossing F5, F6, F7 ~ 1st week of June ~ 4th week of June ~ Aug/Sep
Crossing C7, C8, C9 ~ 1st week of June ~ 4th week of June ~ Aug/Sep
Segment 10 & 11 ~ 2nd week of June ~ 2nd week of July ~ Sep/Oct

EXTRACTION – PPIP SEGMENT – CROSSING MAP